Status Planned
Created by Paolomee Udani
Created on Jul 19, 2021

Resource Status - Update percentage base of quantity

If a task is planned for 10 days to pour 100 cubic meters of concrete. The user would like to be able to update the quantity (cubic meters) using the Field app - Status update